Back to orders
VB-10388: Mark & Ellie Dunn
Shopify SIM-1038848 Linden Park, Hull HU5
Ordered
Tue 8 Sep
Ready by
Fri 2 Oct
Internal QC deadline
Deliver by
Tue 20 Oct
Customer promise. Calculated at order entry (+42 days)
Delivery date
Tue 6 Oct
Confirmed
Route DR-1006 locked (protected, same date)
Actual finished
Not yet
All units passed final QC
Actual delivered
Not yet
Set only by a delivery completion (POD) record
Intake and mapping
All lines mapped
Production
Rework
0 of 1 production pieces complete
Invoice
Not triggered
Delivery
Packed volume 1.85 m³
Delivery postcode HU5 3QT
Eligible runs: Hull and East Riding (district HU5)
On DR-1006 Hull and East Riding. Delivery date Tue 6 Oct, Confirmed (route locked). Readiness: At risk: Ready-by already passed
Route is locked; it is never changed automatically.
Journey
- 1Order received
Tue 8 Sep via Shopify
- 2Variant mapping
All lines mapped to base products
- 3Jobs and routes
1 job created for mapped lines
- 4Plan
1 job unscheduled: ready-by already passed (accepted plan)
- 5Production
Work in progress
- 6QC
QC failed, rework open
- 7Dispatch and delivery
DR-1006 Hull and East Riding, Tue 6 Oct (locked)
- 8Invoice
Triggered at dispatch (simulated). Not yet.
Order lines
- 1 x 7th Heaven Maxi - 3 Seater Sofa, Soft Woven Chenille / FjordShopify SKU zf0009255Built as 1 x 7th Heaven Maxi 3 Seater per sold unit, fabric Soft Woven Chenille / Fjord.1 production job from this one Shopify line (production build version 1, kept as used at import).
Job VB-10388-1 · 7th Heaven Maxi 3 Seater · Soft Woven Chenille / Fjord
Unscheduled: Ready-by already passedJob detail
Frame
Covers
Cushions
Fabric cutWed 30 Sep
Done
std 37m · act 33m
WoodmillWed 30 Sep
Done
std 42m · act 44m
Sew mainThu 1 Oct
Done
std 1h 35m · act 1h 36m
after Fabric cut
Sew cushionThu 1 Oct
Done
std 47m · act 54m
after Fabric cut
Frame assyThu 1 Oct
Done
std 1h 03m · act 1h 11m
after Woodmill
UpholsteryFri 2 Oct
Done
std 2h 06m · act 2h 01m
after Frame assy + Sew main
Cushion fillFri 2 Oct
Done
std 21m · act 20m
after Sew cushion
Final inspFri 2 Oct
DoneQC fail
std 16m · act 14m
after Upholstery + Cushion fill
Cushion seam puckered on seat cushion 2
Rework (consumes capacity)
Rework: Sew cushionMon 5 Oct
Not started
std 25m
Rework: re-sew seat cushion 2
Rework: Final inspMon 5 Oct
Not started
std 10m
Re-inspection after rework
Cutting and frame components run in parallel. cutting branches into main covers and cushion covers. upholstery joins frame and main cover, and cushions rejoin at QC. only this product's steps are shown. Days are from the incoming draft plan.
| Step | Incoming draft | Accepted plan | Shop floor |
|---|---|---|---|
| Fabric cut · 37m std | Wed 30 Sep | Done | done on Wed 30 Sep |
| Woodmill · 42m std | Wed 30 Sep | Done | done on Wed 30 Sep |
| Sew main · 95m std | Thu 1 Oct | Done | done on Thu 1 Oct |
| Sew cushion · 47m std | Thu 1 Oct | Done | done on Thu 1 Oct |
| Frame assy · 63m std | Thu 1 Oct | Done | done on Thu 1 Oct |
| Upholstery · 126m std | Fri 2 Oct | Done | done on Fri 2 Oct |
| Cushion fill · 21m std | Fri 2 Oct | Done | done on Fri 2 Oct |
| Final insp · 16m std | Fri 2 Oct | Done | done on Fri 2 Oct |
| Sew cushion (rework) · 25m std | Mon 5 Oct | Unscheduled: Not placed: job could not be planned | not started |
| Final insp (rework) · 10m std | Mon 5 Oct | Unscheduled: Ready-by already passed | not started |
History (structured audit)
Baseline: Seeded demo order as created
Ready by Fri 2 Oct, deliver by Tue 20 Oct, delivery date as recorded then Tue 6 Oct. Lines: 1 x 7th Heaven Maxi - 3 Seater Sofa, Soft Woven Chenille / Fjord.
- AU-0001 · 12:01:05Plan acceptedPlan v1Plan V1 (simulated demo baseline): 22 jobs planned, 6 unscheduledBy Demo setup. Reason: Simulated baseline: finite-capacity plan computed by the scheduler for the pre-import demo workload. Not an approval by Rob or Vale.. Orders: STK-0007, VB-10371, VB-10388, VB-10395, VB-10399, VB-10402, VB-10404, VB-10406, VB-10407, VB-10409, VB-10410, VB-10412, VB-10415, VB-10418, VB-10421
version none 1 basis none (demo setup) none planned none 22 unscheduled none 6 unscheduledJobIds none J-VB-10388-1; J-VB-10395-1; J-VB-10399-1; J-VB-10402-L1-1-ZENA-1; J-VB-10402-L1-1-ZENC-1; J-VB-10402-L1-1-ZENC-2 simulatedBaseline none true
Activity for this order
- ReworkRework created, consumes sewing capacity
- QC failedCushion seam puckered on seat cushion 2
- CompletedSimulated history
- CompletedSimulated history
- CompletedSimulated history
- StartedSimulated history
- StartedSimulated history
- StartedSimulated history
- CompletedSimulated history
- CompletedSimulated history
- CompletedSimulated history
- StartedSimulated history