Unmapped variant: Serenity - 3 Seater Sofa, Luxe Woven Velvet / Paprika
Shopify SKU zl0013653 on VB-10421 (1 unit) has no production product. No job or route exists until a person maps it. The system will not guess.
Shopify SKU zl0013653 on VB-10421 (1 unit) has no production product. No job or route exists until a person maps it. The system will not guess.
Historical example scenario. Seat cushion seam failed QC on Fri 2 Oct. 25 min sewing rework plus re-inspection. Delivery on Tue 6 Oct at risk.
Operator reported Material issue on VB-10399 Fusion 3 Seater. Upholstery tomorrow depends on this frame.
Rework and re-inspection must finish today to keep the locked Hull route. Customer notification via Track-POD is simulated.
The next step starts at least 1 working day after the step it needs. The incoming draft puts some dependent steps closer to the step they need than that (for example QC too soon after upholstery). Affects VB-10388, VB-10395, VB-10399, VB-10402, VB-10404, VB-10406, VB-10407, VB-10409 and 6 more. The computed plan follows the rule; the draft is left unchanged.
Ready-by already passed. Ready-by 2026-10-02 is before today. 2 operations not placed. Ready by 2026-10-02, delivery 2026-10-06 (protected route, not moved). No dates were changed.
No capacity in window. No working day left: must start on or after 2026-10-05 (predecessor plus 1 working day gap, or today) but finish by 2026-10-02. 3 operations not placed. Ready by 2026-10-05, delivery 2026-10-07 (protected route, not moved). No dates were changed.
Blocked by reported issue. Operation is blocked by a reported issue. Not planned until it is cleared. 6 operations not placed. Ready by 2026-10-06, delivery 2026-10-08 (protected route, not moved). No dates were changed.
No capacity in window. No working day left: must start on or after 2026-10-05 (predecessor plus 1 working day gap, or today) but finish by 2026-10-02. 8 operations not placed. Ready by 2026-10-07, delivery 2026-10-09 (protected route, not moved). No dates were changed.
No capacity in window. No working day left: must start on or after 2026-10-05 (predecessor plus 1 working day gap, or today) but finish by 2026-10-02. 8 operations not placed. Ready by 2026-10-07, delivery 2026-10-09 (protected route, not moved). No dates were changed.
No capacity in window. No working day left: must start on or after 2026-10-05 (predecessor plus 1 working day gap, or today) but finish by 2026-10-02. 8 operations not placed. Ready by 2026-10-07, delivery 2026-10-09 (protected route, not moved). No dates were changed.