Vale BridgecraftBridgecraft OS
OperatorDemo dataDemo date Mon 5 Oct 2026 (fixed)
Back to orders

VB-10418: Daniel Okoye

Shopify SIM-1041827 Beech Walk, Leeds LS6

Ordered
Thu 17 Sep
Ready by
Tue 13 Oct
Internal QC deadline
Deliver by
Thu 29 Oct
Customer promise. Calculated at order entry (+42 days)
Delivery date
Thu 15 Oct
Scheduled
Proposed route DR-1015, still tentative
Actual finished
Not yet
All units passed final QC
Actual delivered
Not yet
Set only by a delivery completion (POD) record
Intake and mapping
All lines mapped
Production
Planned
0 of 1 production pieces complete
Delivery
Scheduled, route to confirm DR-1015
Open route DR-1015
Invoice
Not triggered

Delivery

Packed volume 1.58 m³
Delivery postcode LS6 2UE
Eligible runs: West Yorkshire (district LS6)
On DR-1015 Leeds. Delivery date Thu 15 Oct, Scheduled, awaiting confirmation. Readiness: On plan: QC by Tue 13 Oct

Journey

  1. 1Order received

    Thu 17 Sep via Shopify

  2. 2Variant mapping

    All lines mapped to base products

  3. 3Jobs and routes

    1 job created for mapped lines

  4. 4Plan

    1 job planned (accepted plan)

  5. 5Production

    Not started

  6. 6QC

    Not reached

  7. 7Dispatch and delivery

    DR-1015 Leeds, Thu 15 Oct (proposed)

  8. 8Invoice

    Triggered at dispatch (simulated). Not yet.

Order lines

  • 1 x Fusion - 3 Seater Sofa, Plush Chenille / Maple
    Shopify SKU zl0015162
    Built as 1 x Fusion 3 Seater per sold unit, fabric Plush Chenille / Maple.1 production job from this one Shopify line (production build version 1, kept as used at import).

Job VB-10418-1 · Fusion 3 Seater · Plush Chenille / Maple

PlannedJob detail
Frame
Covers
Cushions
Fabric cutFri 9 Oct
Not started
std 28m
WoodmillFri 9 Oct
Not started
std 32m
Sew mainMon 12 Oct
Not started
std 1h 12m
after Fabric cut
Sew cushionMon 12 Oct
Not started
std 36m
after Fabric cut
Frame assyMon 12 Oct
Not started
std 48m
after Woodmill
UpholsteryTue 13 Oct
Not started
std 1h 36m
after Frame assy + Sew main
Cushion fillTue 13 Oct
Not started
std 16m
after Sew cushion
Final inspTue 13 Oct
Not started
std 12m
after Upholstery + Cushion fill

Cutting and frame components run in parallel. cutting branches into main covers and cushion covers. upholstery joins frame and main cover, and cushions rejoin at QC. only this product's steps are shown. Days are from the incoming draft plan.

StepIncoming draftAccepted planShop floor
Fabric cut · 28m stdFri 9 OctThu 8 Oct · Jason · 28m clock
not started
Woodmill · 32m stdFri 9 OctThu 8 Oct · Jonathan Calder · 32m clock
not started
Sew main · 72m stdMon 12 OctFri 9 Oct · Donna Burton · 1h 12m clock
not started
Sew cushion · 36m stdMon 12 OctFri 9 Oct · Donna Burton · 36m clock
not started
Frame assy · 48m stdMon 12 OctFri 9 Oct · Phillip Wowk · 48m clock
not started
Upholstery · 96m stdTue 13 OctMon 12 Oct · James Haste · 1h 36m clock
not started
Cushion fill · 16m stdTue 13 OctMon 12 Oct · Charlotte Mitchell · 16m clock
not started
Final insp · 12m stdTue 13 OctTue 13 Oct · Paul Stott · 12m clock
not started

History (structured audit)

Baseline: Seeded demo order as created
Ready by Tue 13 Oct, deliver by Thu 29 Oct, delivery date as recorded then Thu 15 Oct. Lines: 1 x Fusion - 3 Seater Sofa, Plush Chenille / Maple.
  • AU-0001 · 12:01:05Plan acceptedPlan v1Plan V1 (simulated demo baseline): 22 jobs planned, 6 unscheduled
    By Demo setup. Reason: Simulated baseline: finite-capacity plan computed by the scheduler for the pre-import demo workload. Not an approval by Rob or Vale.. Orders: STK-0007, VB-10371, VB-10388, VB-10395, VB-10399, VB-10402, VB-10404, VB-10406, VB-10407, VB-10409, VB-10410, VB-10412, VB-10415, VB-10418, VB-10421
    versionnone1
    basisnone (demo setup)none
    plannednone22
    unschedulednone6
    unscheduledJobIdsnoneJ-VB-10388-1; J-VB-10395-1; J-VB-10399-1; J-VB-10402-L1-1-ZENA-1; J-VB-10402-L1-1-ZENC-1; J-VB-10402-L1-1-ZENC-2
    simulatedBaselinenonetrue

Activity for this order

  • OrderSimulated Shopify order received