Back to orders
VB-10418: Daniel Okoye
Shopify SIM-1041827 Beech Walk, Leeds LS6
Ordered
Thu 17 Sep
Ready by
Tue 13 Oct
Internal QC deadline
Deliver by
Thu 29 Oct
Customer promise. Calculated at order entry (+42 days)
Delivery date
Thu 15 Oct
Scheduled
Proposed route DR-1015, still tentative
Actual finished
Not yet
All units passed final QC
Actual delivered
Not yet
Set only by a delivery completion (POD) record
Intake and mapping
All lines mapped
Production
Planned
0 of 1 production pieces complete
Invoice
Not triggered
Delivery
Packed volume 1.58 m³
Delivery postcode LS6 2UE
Eligible runs: West Yorkshire (district LS6)
On DR-1015 Leeds. Delivery date Thu 15 Oct, Scheduled, awaiting confirmation. Readiness: On plan: QC by Tue 13 Oct
Journey
- 1Order received
Thu 17 Sep via Shopify
- 2Variant mapping
All lines mapped to base products
- 3Jobs and routes
1 job created for mapped lines
- 4Plan
1 job planned (accepted plan)
- 5Production
Not started
- 6QC
Not reached
- 7Dispatch and delivery
DR-1015 Leeds, Thu 15 Oct (proposed)
- 8Invoice
Triggered at dispatch (simulated). Not yet.
Order lines
- 1 x Fusion - 3 Seater Sofa, Plush Chenille / MapleShopify SKU zl0015162Built as 1 x Fusion 3 Seater per sold unit, fabric Plush Chenille / Maple.1 production job from this one Shopify line (production build version 1, kept as used at import).
Job VB-10418-1 · Fusion 3 Seater · Plush Chenille / Maple
PlannedJob detail
Frame
Covers
Cushions
Fabric cutFri 9 Oct
Not started
std 28m
WoodmillFri 9 Oct
Not started
std 32m
Sew mainMon 12 Oct
Not started
std 1h 12m
after Fabric cut
Sew cushionMon 12 Oct
Not started
std 36m
after Fabric cut
Frame assyMon 12 Oct
Not started
std 48m
after Woodmill
UpholsteryTue 13 Oct
Not started
std 1h 36m
after Frame assy + Sew main
Cushion fillTue 13 Oct
Not started
std 16m
after Sew cushion
Final inspTue 13 Oct
Not started
std 12m
after Upholstery + Cushion fill
Cutting and frame components run in parallel. cutting branches into main covers and cushion covers. upholstery joins frame and main cover, and cushions rejoin at QC. only this product's steps are shown. Days are from the incoming draft plan.
| Step | Incoming draft | Accepted plan | Shop floor |
|---|---|---|---|
| Fabric cut · 28m std | Fri 9 Oct | Thu 8 Oct · Jason · 28m clock | not started |
| Woodmill · 32m std | Fri 9 Oct | Thu 8 Oct · Jonathan Calder · 32m clock | not started |
| Sew main · 72m std | Mon 12 Oct | Fri 9 Oct · Donna Burton · 1h 12m clock | not started |
| Sew cushion · 36m std | Mon 12 Oct | Fri 9 Oct · Donna Burton · 36m clock | not started |
| Frame assy · 48m std | Mon 12 Oct | Fri 9 Oct · Phillip Wowk · 48m clock | not started |
| Upholstery · 96m std | Tue 13 Oct | Mon 12 Oct · James Haste · 1h 36m clock | not started |
| Cushion fill · 16m std | Tue 13 Oct | Mon 12 Oct · Charlotte Mitchell · 16m clock | not started |
| Final insp · 12m std | Tue 13 Oct | Tue 13 Oct · Paul Stott · 12m clock | not started |
History (structured audit)
Baseline: Seeded demo order as created
Ready by Tue 13 Oct, deliver by Thu 29 Oct, delivery date as recorded then Thu 15 Oct. Lines: 1 x Fusion - 3 Seater Sofa, Plush Chenille / Maple.
- AU-0001 · 12:01:05Plan acceptedPlan v1Plan V1 (simulated demo baseline): 22 jobs planned, 6 unscheduledBy Demo setup. Reason: Simulated baseline: finite-capacity plan computed by the scheduler for the pre-import demo workload. Not an approval by Rob or Vale.. Orders: STK-0007, VB-10371, VB-10388, VB-10395, VB-10399, VB-10402, VB-10404, VB-10406, VB-10407, VB-10409, VB-10410, VB-10412, VB-10415, VB-10418, VB-10421
version none 1 basis none (demo setup) none planned none 22 unscheduled none 6 unscheduledJobIds none J-VB-10388-1; J-VB-10395-1; J-VB-10399-1; J-VB-10402-L1-1-ZENA-1; J-VB-10402-L1-1-ZENC-1; J-VB-10402-L1-1-ZENC-2 simulatedBaseline none true
Activity for this order
- OrderSimulated Shopify order received